Day 8 (20.04.2012) - Temporary Fencing Up

Temporary fencing is up. Our Austral Access Fawn bricks are delivered as well. Corrected construction drawings received and posted back to builder.



Posted by beckybecs at 1:18 PM
Email ThisBlogThis!Share to XShare to FacebookShare to Pinterest
Labels: base stage, carlisle homes baltimore

No comments:

Post a Comment

Newer Post Older Post Home
Subscribe to: Post Comments (Atom)

Views

Reference Sites

  • How to Paint Interior Surfaces
  • How to Apply Sealant
  • Patrenza Blinds
  • Concept Concrete
  • Elvin's Concreting

Labels

  • baltimore (2)
  • baltimore 40 (2)
  • barramundi (1)
  • base stage (7)
  • carlisle homes (2)
  • carlisle homes baltimore (13)
  • carlisle homes baltimore 40 (3)
  • completion (2)
  • contract (1)
  • fixing stage (2)
  • frame (1)
  • frame stage (4)
  • Frames Inspection (1)
  • handover (1)
  • keys collection (1)
  • lockup stage (4)
  • New Homes Inspection (1)
  • Pre Plaster Inspection (1)
  • reestablishment survey (1)
  • reinspection (1)
  • settlement (1)
  • site scrape (1)
  • site start (1)
  • slab (2)
  • valuation (1)

Blog Archive

  • ▼  2012 (26)
    • ►  August (4)
    • ►  July (2)
    • ►  June (4)
    • ►  May (8)
    • ▼  April (7)
      • Day 14 (26.04.2012) - Site updates
      • Day 8 (20.04.2012) - Temporary Fencing Up
      • Day 6 and 7 (18-19.04.2012) - Site Updates
      • Day 5 (17.04.2012) - The day after site scrape
      • Day 4 (16.04.2012) - Site scrape
      • Day 1 (13.04.2012) - Site scrape postponed
      • Site start date set!
    • ►  February (1)
Picture Window theme. Theme images by bloodstone. Powered by Blogger.